Hi All,
We have recently moved from old plant to a new plant code set up. For decommissioning of old plant, this is what I could think of
1. Remove MRP lists via MD08/MS08.
2. Remove PIRs via MD74/5.
3. Removed plant from MRP execution batch ...
Hello all,
This behavior seems to be across the plants.
When displayed via MD04, the PReq quantity is different than that shown in MD05. After you go to display mode, the values are same. So, why is the displayed quantity different?
To the lef...
Hello All,
We have a requirement for maintaining the forecasts for new product introduction. So, was reviewing the option of using Product Life Cycle.
Here I see the attribute PRDID is associated with material in my case. However the requirement...
Hello all,
Need guidance on the transport strategy for planning areas. In a project, where there are multiple roll outs
1. Should we have one single Production Area rather than multiple region wise?
2. While doing the transports, is it ok to ha...
All,
This topic has appeared earlier. However, could not conclude.
Can you guide on the following.
1. Requirement is to have the attachments in Maintenance plan flow to the orders.
2. We do not use task list.
Is it possible via config OR AB...
Hi Dominik,Am aligned to your comments. In this case however, there are no manual changes. The PReq # that is seen in MD05 has a different qty displayed. When you go to the PReq details, the quantity is different. Thanks,Sameer
Hi Piyush,Yes, the same is done.It appears (pending confirmation), the field length of 100 for case UPC is the hindrance. The limit for field length is 60.Thanks