Hi All,
we have a requirement that system should propose a warning message if all steps in PI sheet are not completed before completing process order in CO60.
How we can achieve this?
Regards,
Hello All,
Below is the set up for this.
FG:10001108 (X0 APO planned)SFG:40001118
Raw: 86101615
FG has the planned order for 04th Nov and it created the dep req for SFG for same date 04th Nov. But it is not generating the Raw material req for...
bom.png
pr.png
Hello All,
I am facing one issue.
we are having a header material (A) with below details:
Proc Type: F
Special Proc Type: 30
Now under this header material a BOM comp (B) is there with below details:
Proc Type: F
Spe...
md04.pngmd04-1.png
Hello All,
Material data
MRP type: X0
Strategy group: 52
SPK: 46 Transfer from 1000
Lot size: EX
Min lot size: 4
As attached in the screenshot there are VSE requirements but we don't see the planned orders generated...
Hello All,
I searched on this forum before raising this question but did not find the issue. So creating a fresh question.
Material data:
MRP type: PD
Lot size: EX
Safety Stock: 2
Initial stock: 0
Rescheduling Horizon: 100
Attached is...
Hello,For another material I can see for X0 I can see Sock planned orders in MD04.So how these planned orders are generated.Is there something I am missing
Thanks Dominik.So the next steps for business is to convert PR (For Safety stock) to PO and proceed further.And delete the already created PO (1 qty each) Excep 20will deleting the PO cause any impact on business?But the question still remains why sy...