I changed for one material status in advance planning in mm02 to deactivate for planning Now I want to make it active for plannning. Please let me how to do it.
I have a strange case in my PPDS. I have one material with Fc req/ PIRs in RRP3 view andThose PIRs are not their in MD04.I want to delete those PIRs in RRP3 but it is not happening. I tried using /sapapo/ md74 and MD74.  Please help me out and there ...
We will receive forecast from kinaxis daily but before receiving the forecast we need to delete all existing planned independent requirements. How to delete PIRs in mass.