Hello All
Just checking is there any option to copy key figure notes from one key figure to other in same planning area
I understand that notes are stored at planing area level and no direct way to do it, but any new functionality that has been ...
Hello,
Is there any way, we can achieve the PAL confirmation passing with some tolerance value in % without any custom development.?
Business wants to get allocation check to pass with 5% tolerance above the active allocation, as its trigger a lo...
Hello
During ATP check the backward scheduling is not confirming the sales order on requested delivery date.
Ex:
There is enough inventory at location to cover the requirement.
Lets assume current date when order is being created as 9/11
I...
Hello All.
We using block planning in PPDS and the orders planned and scheduled at block limits. So, we see the Avail date in RRP3 for Receipts and Requirements for that orders are in line with Block end date and Block start date.
But these da...
Hello,Scheduling is done in APO and not in ECC in this scenario.Condition records are maintained in APO for PICK/LOAD/UNLD. TRAN is determined through T lane between customer Tran zone and Delivery location. screen shot below.In OLVY dlvry and trans ...
Hello Brahmankar,Thanks for response.!Condition records are maintained. No shipping calendar maintained in APO side. Calendar on shipping point on ECC doesn't have any holidays and they work 24/7.Enclosed Screen shots of schedule lines and scheduling...
Hello Jomerce,
Thanks for sharing such an great article.
wanted some insight on below:
I work in Paper mill industry and we use CDP very extensively in Block Planning on APO PPDS and in process to migrate to S4HANA with Embedded PPDS from APO PPDS...