Dear Fellow SAP People,
You may have experienced the same requirement before or asked the same question related to mine that was successfully answered. You may share it here in this thread.
Meanwhile, to give the details of my requirement:
->De...
The Plan Costs could be different from the Target Costs.The Target Costs are normally based on Standard Cost Estimate, depending on the configuration of Variance Calculation, under Define Target Cost Versions. While Plan Costs are normally set based ...
You may check the status of your Process / Production Orders. Normally, those Orders with only Versions 1 or 2 in COSP Table are just having Released Process / Production Orders. Meaning, they have not undergone any Goods movements nor Confirmation y...
Actually in KSS1 (Variance Calculation), you may click on the Variances so you would see the calculation and explanation per category (if your variance was properly configured).
The statements are quite cluttered. Maybe you could help out to elaborate the step-by-step transactions you did. And please include the movement type used on your consumption because it is linked to your requirement where you don't want the consumpti...
You may check the MMRV (Logistics Period) if the current period is 007. Because you cannot perform ML Closing for the current open Logistics Period. The current period must be 008 before you can do the CKMLCP (ML Closing for period 007).