Dear experts,Is there a way to get my scheduled preventive maintenance orders having basic start date at the beginning of the month and the basic finish at the end of the month? I plan to have this automated for all work orders.
M Terence, thank you for the guidance, i appreciate it.Just to elaborate further on this topic so everyone can benefit;Date Shifts maintained in the Priority do not come into play when you are scheduling Maintenance Plans.To address this you can add ...
Hi Sank_n,Thank you for your response but this wasnt my issue, i should have been more descriptive.I would like to schedule a maintenance plan such that i could set its basic start & basic finish dates 1 month apart. Upon some research on the communi...