Reading again what you customized: transaction code OPPR is meant for MRP groups. Did you maintain a MRP group in the material master? And what are the settings in transaction code OPPQ (plant parameters for MRP)?
Hi Guillaume,By applying an MRP type with a planning time fence in the material master, we could avoid that planned orders pop up between production orders for the next coming days. Then we are able to execute an availability check for planned orders...
Hi Guillaume,Are you using both discrete and repetitive manufacturing? And did you consider to use transaction code MDVP for the availability check of planned orders instead?
Hi Shankar,When you are only dealing with manufacturing of 6 different kinds of biscuits, I would choose at first to investigate repetitive manufacturing with batch traceability. This is the least complicated solution.Second best option would be PP-P...
Hi Aqueel,For reorder point planning the rule of thumb is that Reorder Point is the sum of "Safety Stock" and the "Demand During the Lead Time". In your example, the safety stock is 50 PC and the demand during lead time is 90 PC. I would expect a reo...