Dear Experts,

Previously, we have used the maximum number of Communication Scenarios in a solution in SAP Cloud Application Studio for integration.

Now, we have the new requirement to disconnect with the old system and connection with the new system. However, the .csd object has been deployed to Production tenant so we can neither delete the obsolete .csd object nor create new .csd for the new connection as there is no room left.

Please help to advice what could we do in this case. Is there any solution for this?

View Entire Topic
ashishsingh1987
Advisor
Advisor
0 Kudos

Hello Giang,

If I may ask a small query on this:

Is it a point to point connection or you are using any middle-ware system to integrate the two system?

Regards,

Ashish Singh

0 Kudos

Hello Ashish,

Thanks for your reply.

The new connection is a point to point connection while the old one is connected through PI.

Regards,

Giang.

ashishsingh1987
Advisor
Advisor
0 Kudos

Hi Giang,

If there is a middle-ware around the previous connection, you may try the below work around and see if it makes sense & works: (I have limited knowledge about PI as such) & Also assuming that the new connection can also be established via PI and Point to Point is not mandatory approach.

1) Let the current connection be in place (.csd files etc in C4C). Let the data move out from C4C as per old WSDL file format.

2) In PI, create a new mapping and just map the data coming from C4C to the new WSDL files

3) Change your destination url in the PI system.

Regards,

Ashish Singh