Which of the following statements is true?
1. A firmed order can be scheduled/rescheduled, but a date fixed order can't be scheduled/rescheduled using scheduling heuristics.
2. Both the firmed order and the date fixed order can be scheduled/rescheduled using scheduling heuristics.
3. Neither the firmed order nor the date fixed order can be scheduled/rescheduled using scheduling heuristics.
4. A firmed order can't be scheduled/rescheduled, but a date fixed order can be scheduled/rescheduled using scheduling heuristics.
I've found on the Internet that 1. is True but cannot find the explenation even in TS421/422.