Dear Experts,
I'm trying to implement the Result Analysis functionality for the first time, using the POC from the progress analysis,
I made the required configurations/master data, but i'm facing the problem that when i run the result analysis transaction KKA2, the POC is not being updated.
System keeps fetching the 1st POC which was recorded on the progress tab of WBS (CJ20N) the 1st time i ran KKA2, and when the POC of the WBS changes in CJ20N, those changes are not updated in KKA2.
The below is some screenshots of the setup i made:
Now I try to run KKA2 for period 10.2015, system should fetch the current progress (80%), however it keeps fetching the progress where recorded the last time i ran it (67.5%)
Note: The progress of period 10.2015 was 67.5% the 1st time i tested KKA2, and I changed it manually to 80%.
Appreciate your valuable help.
Hi Byalya,
I am agree with Ken approach with Progress analysis , first you write the POC to the statistical Key figure, Then your RA will read this POC, will need update in value based from SKF .
Try this .
Regards
Asish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You have to run progress analysis first and it will write the POC to a Statistical Key Figure. RA will read this POC from the SKF.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I notice you have assigned a POC method Q. Please try this with V (value based) POC and see if this make a difference.
Cant tell if the RA cut off period is current from the date but you may want to take a look at that as well.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
12 | |
10 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.