Hello Experts,
I have Created one PO and then MIGO Against PO No.
after that I have created MIRO against that PO No.
Example; PO no.-450005
vendor-110010........PO Data
MiGO - 50008
vendor-110010........Migo Data
MIRO -
PO no.-450005
vendor-214100........MIRO Data
PO And MIGO vendor is SAME
BUT in MIRO vendor is reflect different.
Is there any solution.
Thanks And Regards,
Sam
2016 Feb 04 8:01 AM
Have u checked, double click on the Po Number At Miro item level.Then it will take us to me23n
2016 Feb 04 11:22 AM
Hello Dear,
PO & MIGO vendor is same.like(110010)
In MIRO vendor is SAME Upto simulation(110010.
after simulation if we go to post document it will change vendor(214100).
Thanks & Regards
Sam
2016 Feb 04 12:33 PM
2016 Feb 05 5:52 AM
Hello sir,
I check for FI substitution but it is not their for our system.
This is not permanent issue , it arises sometimes.
Is there any BADI to solve this issue or how to do this??
Thanks and Regards.
Sam
2016 Feb 05 10:19 AM
Did you also check for
Regards,
Raymond