‎2005 Jul 02 8:21 AM
Hi,
I created a Work Order for Maintenance . How to associate Bill Of Materials/BOM to it and release/confirm order.?
Is there any online document/help on this?
Can anyone help me out?
Thanks
Prabha
‎2006 Apr 28 9:38 AM
there are two ways to do this,
1. create a equipment bill of material and assign the equipment bill of material to the maintenance work order.
2. if equipment bill of material is not available then create the work order and assign the maintenance spares manually in the maintenance work order.
Please reward for the same.