2009 Aug 19 5:42 AM
Hi,
I need to update Phase value for a PM notification, after its completion. This process will be triggered by a custom RFC called from PORTAL side. Could you suggest how to update phase value for PM notification confirmation/completion.
Regards,
Pulokesh
2009 Aug 19 5:45 AM
check "BAPI_ALM_NOTIF_DATA_MODIFY".bapis are remote enabled so it might serve the purpose.
Hi,
I need to update Phase value for a PM notification, after its completion. This process will be triggered by a custom RFC called from PORTAL side. Could you suggest how to update phase value for PM notification confirmation/completion.
Regards,
Pulokesh
2009 Aug 19 5:45 AM
check "BAPI_ALM_NOTIF_DATA_MODIFY".bapis are remote enabled so it might serve the purpose.
2009 Aug 19 5:52 AM
Hi,
Can you tell me where to pass the phase value in the BAPI that you have mentioned. Can anyone tell how to update Notification phase value while its closure/completion.
Regards,
Pulokesh
Edited by: Pulokesh Karmakar on Aug 19, 2009 11:16 AM
2009 Aug 20 9:52 AM
The issues was solved by using BAPI BAPI_ALM_NOTIF_CLOSE. Thanks for the advices.