‎2008 Feb 18 11:06 AM
is there any BAPI or FM for this : update VSTAT field in NAST table
‎2008 Feb 18 11:10 AM
Hi,
You can issue the Output for the respective documents. Then the processing status will get changed automatically.
Regards,
Ashok
‎2008 Feb 18 11:12 AM
Hi
I don't believe it, u can try to check programs like RSNAST00, here the table is updated directly. What do you need to do?
Max
‎2008 Jul 16 6:03 PM
I know it's too late but i need it too and I want to avoid others spent time searching for it
RV_MESSAGE_UPDATE_SINGLE
‎2008 Jul 16 6:20 PM
The NAST status will change once you process the output type.
Check whether the output type is set immediate update or scheduled for periodic job ( NAST-VSZTP).
If it is set as a immediate update then the status will change as soon as you carried out the transaction. If it is scheduled for periodic job then you have to execute the program RSNAST00 with specific object key and output type.