Table for Status 'PRIR' (Process Interruption) in Process Order

Former Member
0 Likes
485

Hi

When we do process interruption of a Process Order , the confirmation status changes to 'PRIR' . In which table is this entry saved?

It is not available in JEST table.

Thanks in advance.

Laxman.

2 REPLIES 2
Read only

Former Member
0 Likes
388

Hi

Kindly try to search JSTO.

Regards,

Read only

0 Likes
388

I found out the answer. It can be done through JEST table itself.

We need to use the OBJNR we get from afvc , into JEST and check the INACT field for STAT = I0108.