2006 Sep 14 6:50 PM
hi to all,
pplz help me in the issue,
i am having a field 'mhnk-ausdt' it is rundate in dunning
i need mhnk-ausdt + 7th day day like ex
mhnk-ausdt is 14th sep and 7th day of it is 21st sep
how can i achieve this.
thanks in advance
kiran kumar
Message was edited by: kiran kumar
2006 Sep 14 8:10 PM
Hi Kiran,
It is very simple since all date type fields in abap (in tables - type 'DATS', in programs - type d, also sy-datum in system table, etc.) are treated as simple numbers (integers, if u will...).
This means that if u check the value of these fields (in debugger) u will find the date today is 20060914 - this is YYYYMMDD format but it is treated as a number. With numbers u can do arithmetic operations: add, sub, etc.
Now all u have to do is add 7 and get the date u r looking for...
U don't have to check if it went to the next month or year since the system knows to do that. For example: if your field, mhnk-ausdt, has 30th dec 2006 in it, after adding 2 the result will be 1st jan 2007.
The system will calculate 20061230 + 2 and the result is 20070101.
Hope this covers it...
Igal
(Pls reward if it helps)
hi sid
how to use perfrom control command for getting the desired date
tahnks in advance,
kiran kumar
2006 Sep 14 7:51 PM
Use the function module DATE_IN_FUTURE.
You can add 7 days to the date you pass.
2006 Sep 14 7:58 PM
to add 7 days to field 'MHNK-AUSDT' can be done by
MHNK-AUSDT = MHNK-AUSDT + 7.
The above statement will add 7 days to the date. The above statement has to writted in the print program.
If you want to add the 7 days to the date in the form then you have to use PERFORM control command by passing the 'MHNK-AUSDT'.
In SAPSCRIPT:
/: DEFINE &V_DATE&
/: PERFORM GET_DATE IN PROGRAM ZPROG
/: USING &MHNK-AUSDT&
/: CHANGING &V_DATE&
/: ENDPERFORM
Coding of the calling ABAP program:
REPORT ZPROG.
FORM GET_DATE TABLES IN_PAR STUCTURE ITCSY
OUT_PAR STRUCTURE ITCSY.
data: l_date like sy-datum.
*-- if the date is in MM/DD/YYYY format
READ TABLE IN_PAR WITH KEY MHNK-AUSDT.
IF SY-SUBRC = 0.
l_date+0(4) = IN_PAR-VALUE+6(4).
l_date+4(2) = IN_PAR-VALUE+0(2).
l_date+6(2) = IN_PAR-VALUE+3(2).
ENDIF.
l_date = l_date + 7.
READ TABLE OUT_PAR WITH KEY V_DATE.
IF SY-SUBRC = 0.
write l_date to OUT_PAR-VALUE.
MODIFY OUT_PAR INDEX SY-TABIX.
ENDIF.
ENDIF.
2006 Sep 14 8:02 PM
hi sid
how to use perfrom control command for getting the desired date
tahnks in advance,
kiran kumar
2006 Sep 14 8:10 PM
/: DEFINE &V_DATE&
/: PERFORM GET_DATE IN PROGRAM ZPROG
/: USING &MHNK-AUSDT&
/: CHANGING &V_DATE&
/: ENDPERFORM
Coding of the calling ABAP program:
REPORT ZPROG.
FORM GET_DATE TABLES IN_PAR STUCTURE ITCSY
OUT_PAR STRUCTURE ITCSY.
data: l_date like sy-datum.
*-- if the date is in MM/DD/YYYY format
READ TABLE IN_PAR WITH KEY MHNK-AUSDT.
IF SY-SUBRC = 0.
l_date0(4) = IN_PAR-VALUE6(4).
l_date4(2) = IN_PAR-VALUE0(2).
l_date6(2) = IN_PAR-VALUE3(2).
ENDIF.
l_date = l_date + 7.
READ TABLE OUT_PAR WITH KEY V_DATE.
IF SY-SUBRC = 0.
write l_date to OUT_PAR-VALUE.
MODIFY OUT_PAR INDEX SY-TABIX.
ENDIF.
ENDIF.
2006 Sep 14 8:10 PM
Hi Kiran,
It is very simple since all date type fields in abap (in tables - type 'DATS', in programs - type d, also sy-datum in system table, etc.) are treated as simple numbers (integers, if u will...).
This means that if u check the value of these fields (in debugger) u will find the date today is 20060914 - this is YYYYMMDD format but it is treated as a number. With numbers u can do arithmetic operations: add, sub, etc.
Now all u have to do is add 7 and get the date u r looking for...
U don't have to check if it went to the next month or year since the system knows to do that. For example: if your field, mhnk-ausdt, has 30th dec 2006 in it, after adding 2 the result will be 1st jan 2007.
The system will calculate 20061230 + 2 and the result is 20070101.
Hope this covers it...
Igal
(Pls reward if it helps)