Hi All,

I am facing a problem in creation of Schedule Agreements .

Using me31l am trying to create SA.After entering vendor, plant etc. values it will navigate to header and after filling up the values it goes to item level.

There i enter the material, then netprice, units of measure etc.. will be automatically populated. The target quantity has to be entered manually.

In the next screen i.e. items details screen, again we can enter or change the values of price, target quantity, BOM etc. But these fields are disabled for some combination of vendor and material and enabled for some combination.

Can anyone have idea, why it is disabled for some and enabled for some?

Rgds,

Ram Sri

Hi All,

I am facing a problem in creation of Schedule Agreements .

Using me31l am trying to create SA.After entering vendor, plant etc. values it will navigate to header and after filling up the values it goes to item level.

There i enter the material, then netprice, units of measure etc.. will be automatically populated. The target quantity has to be entered manually.

In the next screen i.e. items details screen, again we can enter or change the values of price, target quantity, BOM etc. But these fields are disabled for some combination of vendor and material and enabled for some combination.

Can anyone have idea, why it is disabled for some and enabled for some?

Rgds,

Ram Sri

2 REPLIES 2
Read only

Former Member
0 Likes
419

Are you creating some with reference to a RFQ and some without reference?

Read only

Former Member
0 Likes
419

Without Reference to contract.