Hello Friends,

I need to upload Planned Independent requirements master data through BDC, i have developed a program but im facing a problem when user want to maintain quantity for back-dated in scheduled lines tab.

for example : if the quantity is maintained for 01.09.2010 , 03.09.2010. and now i want to maintain the quantity for 02.09.2010 but wen i do so the first row data of table control is getting replaced which is not required.

so is it ryte to upload this data through bdc method or not?

Pls suggest.

Regards,

Sunny

1 REPLY 1
Read only

Former Member
0 Likes
484

Hi Sunny,

I'm a total newbie for MD61, but just a suggestion. I have seen that if you switch to tab "Sched.lines" you're able to input quantities for individual days (meaning one row for each day).

Does it make a sense?