1.)How do i calculate the actual costs for Project,WBS wise and Activity wise..Which table will be useful for getting this info..
Also are there costs pertaining to networks?
2.)Please tell me the name of the table to link materials/PR with Projects ,WBS ,Activity and Networks...
Thanks in advance...
‎2007 May 07 11:31 AM
Hi
See the tables
BPEJ - for Budget Data
COST - Activity Type Costs
COSP - Work order Plan/estimated Costs
COEP - Work Order Actual costs
Links between tables
AUFK-pspel = prps-pspnr orders for WBC elements
ebkn-nplnr = afko-aufnr to get PR links
ekkn-nplnr = afko-aufnr To pet PO links
mseg-nplnr = afko-aufnr to get Material Doc links