2010 Jul 22 9:16 PM
HI
I am implementing a note manually, which have instruction like below
-
Manual Pre-Implement. |
-
VALID FOR |
Software Component SCMSNC Supply Network... |
Release 700 Until SAPK-70006INSCMSNC |
Release 701 Until SAPK-70101INSCMSNC |
-
o Open BAdI /SCF/CSV_SETTINGS in SE18
- Add the following 2 methods to interface /SCF/IF_EX_CSV_SETTINGS:
CHANGE_INPUT_ENCODING
CHANGE_OUTPUT_ENCODING
But when I go till point I can able to add the method as it is grayed out
Is there any reason or different way of implementing the note manually?
Regards
Dev
2010 Jul 23 5:48 PM
To implement note manually you need to get the access key. Once you give the access key you can apply the note corrections.
HI
I am implementing a note manually, which have instruction like below
-
Manual Pre-Implement. |
-
VALID FOR |
Software Component SCMSNC Supply Network... |
Release 700 Until SAPK-70006INSCMSNC |
Release 701 Until SAPK-70101INSCMSNC |
-
o Open BAdI /SCF/CSV_SETTINGS in SE18
- Add the following 2 methods to interface /SCF/IF_EX_CSV_SETTINGS:
CHANGE_INPUT_ENCODING
CHANGE_OUTPUT_ENCODING
But when I go till point I can able to add the method as it is grayed out
Is there any reason or different way of implementing the note manually?
Regards
Dev
2010 Jul 23 5:48 PM
To implement note manually you need to get the access key. Once you give the access key you can apply the note corrections.