‎2006 Mar 13 7:28 PM
Could anybody advice with navigation steps for:
"When a user creates a PM Notification and chooses a graded leak the system uses the start date of the day entered. Then the system defaults a finish date based on the grade.
Example: Grade II leak start date 01/27/06 end date 10/24/06
If the Notification is being entered at a later date like today, but we were notified of the leak on Monday 01/23/06 we will do a date over ride on the start date field reflecting 01/23/06 instead of 01/27/06.
The end date doesn't change or recalculate to reflect the correct finish date at the end of the process unless it is done manually. This can become a compliance issue if the dates aren't correct."
Thanks in advance.
‎2006 Mar 15 3:31 AM
Hi
To create a PM Notification, use Tcode IQS1 & select Notification type M1.
Regards,
Suresh Datti