‎2008 Nov 05 2:43 PM
Hi,
I've created a report and I assigned the development to a wrong transport order.
How can I move the task to another transport order?
‎2008 Nov 05 2:46 PM
Please, goto transaction SE09, select your task and follow the menu path Utilities->Reorganize->Reassign Task
‎2008 Nov 05 2:46 PM
Please, goto transaction SE09, select your task and follow the menu path Utilities->Reorganize->Reassign Task
‎2008 Nov 05 2:46 PM
Hi Marshal
place the cursor the the Original transport request where you want to move the task to and hot Ctrl+F11 and give the Transport request number which you wrongly place it and include that task to this Original one.
‎2008 Nov 05 2:52 PM
I think you are meaning workbench transprot request request by transport order. If it is, then yes you can move the task from the wrong transport request. Follow these steps
1. Go to SE10 and find the transport request.
2. Now locate the task under which your report is assigned in the transport request. Now expand the task and right click on your report name and select 'Delete'. It will give some warning message, select yes every time and the report will be removed from the transport request.
3. Now go to SE38 and open your report. Then try to save it. it will again ask for transport request. Now give the correct transport request.
Thanks,
Mainak
‎2008 Nov 05 2:59 PM
Thanks Rajesh and Mainak,
I really wanted the Mainak solution but I didn't realised that I made the wrong question and the Rajesh answer is the answer to my question.
I regarded you both.
‎2008 Nov 05 3:01 PM
Hi Marshal, my answer is a little ahead to your question you can use the solution I provided if you want to add task of others to your transport req number.