2008 May 19 5:41 AM
my BDC program is able to upload the data according to user template.
but one view (work scheduling) is not appearing in mm03.
i checked why it is not coming , found that there is no data for that view.
my requirement even there is no data the (work scheduling) view should come.
waiting for your input
thanks
my BDC program is able to upload the data according to user template.
but one view (work scheduling) is not appearing in mm03.
i checked why it is not coming , found that there is no data for that view.
my requirement even there is no data the (work scheduling) view should come.
waiting for your input
thanks
2008 May 19 5:55 AM
Hi,
Check that work scheduling is selected irregardless of whether there is work scheduling data or not.
Cheers.
...Reward if useful.
2008 May 19 6:04 AM
2008 May 19 6:06 AM
perform bdc_field using 'BDC_CURSOR'
'MSICHTAUSW-DYTXT(17)'.
perform bdc_field using 'BDC_OKCODE'
'=P+'.
perform bdc_field using 'MSICHTAUSW-KZSEL(08)'
'X'.
perform bdc_field using 'MSICHTAUSW-KZSEL(09)'
'X'.
perform bdc_field using 'MSICHTAUSW-KZSEL(10)'
'X'.
perform bdc_field using 'MSICHTAUSW-KZSEL(11)'
'X'.
perform bdc_field using 'MSICHTAUSW-KZSEL(12)'
'X'.
perform bdc_field using 'MSICHTAUSW-KZSEL(13)'
'X'.
perform bdc_field using 'MSICHTAUSW-KZSEL(14)'
'X'.
perform bdc_dynpro using 'SAPLMGMM' '0070'.
perform bdc_field using 'BDC_CURSOR'
'MSICHTAUSW-DYTXT(03)'.
perform bdc_field using 'BDC_OKCODE'
this is for work scheduling
perform bdc_field using 'MSICHTAUSW-KZSEL(14)'
'X'.
i have done recording and put in program.
2008 May 22 4:52 AM
| User | Count |
|---|---|
| 6 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |