Hi,

Our requirement is we should be able to make inbound delivery for

schedule release only for 7 days from the delivery date .That is if

delivery date is 02.12.2013 we should be able to make inbound delivery

only till 09.12.2013.

regards

Suresh S


Hi,

Our requirement is we should be able to make inbound delivery for

schedule release only for 7 days from the delivery date .That is if

delivery date is 02.12.2013 we should be able to make inbound delivery

only till 09.12.2013.

regards

Suresh S

2 REPLIES 2
Read only

Former Member
0 Likes
607

Hi Suresh,

Are you searching for a configuration kind of thing here OR ABAP suggestion. if ABAP coding suggestion please follow the below procedure.

you can call the function module CALCULATE_DATE by passing current date and 7 days(as per your requirement).

It will return you the expected inbound delivery date.

Please let me know if you face any issues here.

Thanks and Regards,

Bhaskar

Read only

0 Likes
607

Hi ,

Our requirement is we should be able to make inbound delivery for

schedule release only for 7 days from the delivery date .That is if

delivery date is 12.12.2013. At the time of doing inbound delivery only schedule lines upto 19.12.2013 should be fetched and we should also make to do inbound deliver , at present in standard it is fetching only schedule quantity upto current date. Please let me know how I can able to modify .

regards

Suresh S