‎2006 Jun 07 9:27 PM
Hi,
I did extend the material using MM01 and when I am using the transaction ME11, I did get a warning message:
"Material 0002345 mainly procured internally (please check your input)".
Can anyone please let me know how to ignore this warning message? Thanks!
‎2006 Jun 07 9:29 PM
‎2006 Jun 07 9:33 PM
You are probably trying to extend a material to purchasing org views whereas you material is not externally procured.
‎2006 Jun 07 9:50 PM
Thanks for the replies!
I want to know what change I should do in MM02, to avoid this message? Thanks!
‎2006 Jun 07 10:13 PM
‎2006 Jun 07 11:04 PM
Hi Saquib,
It's not possible to delete the data in the Purchasing view, because it has been extended from a Finished goods material. Can you please let me know what changes should be done to avoid this?
Thanks!
‎2006 Jun 07 11:31 PM
As per my understanding youre extending material from BDC or lets say manually when you hit extend and after that a pop-up will come that ask for certain views which you want to create or not , just uncheck the pur.view . I guess it works. I cant test it because Im working on HR system .
Thanks
SK
‎2006 Jun 07 11:52 PM
I did try by unchecking pur. view..even then, it does not work.I am still getting maintained procured internally (please check your input)....
‎2006 Jun 07 11:57 PM
Vamsee
I dont have system so I cant try lets wait for some other , who has MM access and let you know the exact thing ..
Thanks
Sk
‎2006 Jun 07 11:57 PM
‎2006 Jun 08 3:15 PM
Hi Rich,
Thanks for the reply. I did change the Procurement type from X to F.But I am still getting
the same warning message.In MRP2, after i changed the Procurement type , in scheduling block,
the field "In-house production" still exists and it is taking as 0 days.Can you please let me
know if I have to make any more changes?
Thanks!
‎2006 Jun 08 4:59 PM
In SPRO transaction, follow the path below.
Implementation Guide for R/3 Customizing (IMG)
-->Logistics - General
-->Material Master
-->Basic Settings
-->Material Types
-->Define Attributes of Material TypesSelect the material type of your material that you are updating. Press the 'Display' icon. In the subsequent screen, check the values for 'Ext. Purchase Orders' and 'Int. Purchase Orders'. If 'Ext. Purchase Orders' = 0, then you cannot procure it externally and so you cannot create a purchasing view to it. If it 1, then both the procurements are allowed but a warning is issued. If you are getting this warning, then probably your material type is configured as 1 for 'Ext. Purchase Orders' as well as for 'Int. Purchase Orders'. Change them both to 2 and you will not get this warning.
But make sure you talk to a MM functional person before you make such changes to the material type just to make your BDC to go through.
Srinivas
‎2006 Jun 09 3:24 PM
Thanks Srinivas. I will check with my Functional people and will get back to you!