2006 Sep 29 3:08 AM
hi All
I need to create a dynamic variant for a background job
to date in the selection screen should be the current date and from date should be 1 month before the current date, is there any way to set this in save variant screen ...
regards
siddhartha
hi All
I need to create a dynamic variant for a background job
to date in the selection screen should be the current date and from date should be 1 month before the current date, is there any way to set this in save variant screen ...
regards
siddhartha
2006 Sep 29 3:21 AM
Hi
Proceed as below:
While saving the variant, the system prompts for Variant name and description, over here you can do the following steps.
1. Check the checkbox(Selection Variable - Under L) for date selection-parameter.
2. Click on "Selection-Variables" button in application toolbar.
3. In the new screen, you will find by default the green light is under "T", click on Orange Light under "D" to make it green.
4. You will find an icon with down arrow symbol for F4 Values. Click on that.
5. Scroll down to find a value "Current date - xxx,current date + yyy". Select the same and "Choose".
6. In the next popup screen give 30 for XXX and 0 for YYY.
7. Save twice.
8. Now you will be back in selection screen, select the variant again to see the data values populated automatically.
Hope the above info helps you.
Kind Regards
Eswar
2006 Sep 29 3:49 AM
2007 Jan 16 11:19 AM
Hi,
I am also facing this problem after we upgraded our CRM system to 5.0 from 4.0. Can you please let me know how to create the dynamic variants in CRM 5.0.
Thanks in advance
Rashit