2008 Sep 09 7:35 AM
Hello Experts,
While using BAPI_material_SAVEDATA,to exend material from one plant to another.Its throwing an error
Currency initial V,current amount 6,000.0000 in MOVINGPR was transferred without a currency.
I search through SDN ,that for currency field I have to update PRICE_UNIt,but price_unit is of thye dec not of currency type.
Plz suggesmr some solution.
Ravi
Hello Experts,
While using BAPI_material_SAVEDATA,to exend material from one plant to another.Its throwing an error
Currency initial V,current amount 6,000.0000 in MOVINGPR was transferred without a currency.
I search through SDN ,that for currency field I have to update PRICE_UNIt,but price_unit is of thye dec not of currency type.
Plz suggesmr some solution.
Ravi
2008 Sep 09 9:45 AM
2009 Feb 21 12:24 PM
Hi gurus,
I am getting below error in bapi While using BAPI_MATERIAL_SAVEDATA,Its throwing an error message as "CURRENCY initial v., currency amount 100,0000 in MOVING_PR was transferred without a currency."
Plz suggesmr some solution.
Satti
2009 Apr 28 7:54 PM
Hi Veeram,
Did you get any answer for this? I am having the same problem.
Thanks,
Le
2009 Apr 28 9:37 PM
2013 Oct 22 12:52 PM
Hi,
make an entry "BWKEY" valuation area same as plant value to get rid of this error.
| User | Count |
|---|---|
| 6 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |