‎2007 Jul 05 8:21 AM
dear all,
let say that i have created mat A with base unit EA and has conversion 1 BOX = 144 EA,
from work order i reserve 1.653 BOX, if i look at resb why BDMNG(requirement quantity) = 239.000, instead of 1.653 * 144 = 238.032. do you know any config or explanation to this?
looks like SAP will round this mat A to 0 decimal, but if i created other mat B with other conversion like 1 JT = 0.5 EA, it will calculated correctly with 3 decimals.
Thanks
‎2007 Jul 05 8:23 AM
Hi
Check the fun modules
UNIT_CONVERSION_SIMPLE or
MD_CONVERT_MATERIAL_UNIT
for the material unit conversion
Reward points for useful Answers
Regards
Anji
‎2007 Jul 05 8:27 AM
hi Anji,
i only change quantity in WO (iw32) , not in custom program. so i can't interupt this.
any other idea?