‎2013 Nov 18 5:42 PM
Dear all,
I have a very hurgent problem:
I have trasported almost 30 Change Request in Production System 1 month ago.
After that the customer did a client copy from PRD into QTY.
I don'think that this could be the cause, but my problem is that now if I go in STMS I have the status of theese Change Request that is grey, as If they should be imported, but are alreaady in!!
Is there a way in order to check when e why the status has chaged?
How can I UNDERSTAND what is happen?
please help me is very hurgent
Regards
‎2013 Nov 18 5:56 PM
Hi Alex,
Please check the versions of all servers(Dev, Qty and Prod).
If it's report, create one more request and move to production.
Arivazhagan S
‎2013 Nov 18 5:56 PM
Hi Alex,
Please check the versions of all servers(Dev, Qty and Prod).
If it's report, create one more request and move to production.