‎2014 Aug 12 6:21 AM
Hi Friends,
i have one issue in Change pointer,
i have creater one material and trasfered it using IDOC but now i want to change the data
of that material usingchange pointer,
so please tell me the way from top to bottom how could i achieve it.
Thanks
Vikash
‎2014 Aug 12 8:37 AM
Go to SALE Tr. -> Modelling and Implementing Business Processes -> Replication of Modified Data
1. Activate Change Pointers - Generally ->F8->Checkbox has to be checked
2. Activate Change Pointers for Message Types ->F8-> Checkbox for the required message type has to be checked
Then run RBDMIDOC to create IDOC for changes.
‎2014 Aug 13 4:33 AM
Hi Aashrith HG,
Thanks For Your help
you gone through theright way.
but i have an issue that after doing this all steps
how would i change the data of material what ever i have created?
where i can change the material data??
Thanks
Vikash
‎2014 Aug 13 7:14 AM
If your questions is, whether a new material created will generate IDOCs after change pointers are activated, the answer is YES. The creation itself will be recorded as a change and the Idoc will be generated.
I created a new material - GWPDFAFCR98765 and saved it. The following record got created in BDCP2.
On running RBDMIDOC, it created the IDOC.(the processed flag is also checked in the screenshot)
please let me know if I have misinterpreted your question.
Regards,
Aashrith.