2007 Sep 20 7:12 AM
Hi Experts,
I have to maintain the change log for the starting date of the WBS element (T code - CJ02 , Field - PRTE-PSTRT ). Change document is not maintained by SAP for the table PRTE , so checking the checkbox of the data element doesn't work out . So I created a customized change document object in SCDO and generated the Functional Module .
How should I proceed from this . My objective is to place this FM where the old and new value of the start date (PSTRT) is accessible . I tried placing the FM in the BADi WORKBREAKDOWN_UPDATE , but I cannot get the new, entered start date? Please help .
Hi Experts,
I have to maintain the change log for the starting date of the WBS element (T code - CJ02 , Field - PRTE-PSTRT ). Change document is not maintained by SAP for the table PRTE , so checking the checkbox of the data element doesn't work out . So I created a customized change document object in SCDO and generated the Functional Module .
How should I proceed from this . My objective is to place this FM where the old and new value of the start date (PSTRT) is accessible . I tried placing the FM in the BADi WORKBREAKDOWN_UPDATE , but I cannot get the new, entered start date? Please help .
2007 Sep 28 5:06 AM
Solved .
Exported the new date using the Implicite Enhacement and imported it in the BADI.