BAPI for CM23

Former Member
0 Likes
513

Hi Experts,

My requirement is to change the Start Date for a Planned Order's operation, based on which system needs to calculate the start and end date for rest of oprations and for Planned order. This is done through CM23 transaction but i need a FM or Bapi to achive this fuctionality.

Tried BAPI_PLANNEDORDER_CHANGE, but it used only to change header data of planned order and not operations Start and End Dates. And BDC seems not possible. 

Please let me know if i can use any FM for this requirement.

Thanks,

Vipin

1 REPLY 1
Read only

Former Member
0 Likes
423

hello,

Did you check FM CLOI_CHANGES_UPL_31 or CO_XT_OPERATION_CHANGE ?

best regards,

swanand