BADI ME_PROCESS_REQ_CUST Not Trigger.

Former Member
0 Likes
1,960

Dear Experts,

I write code in BADI ME_PROCESS_REQ_CUST.  it doesn't contain any error.

i activate Badi with breakpoint. but it not trigger when  i go through MD04.

i want to  debug BADI for the same MD04 for automatic PR generate from MRP.


Thanks And Regards,

SAM.

1 ACCEPTED SOLUTION
Read only

RaymondGiuseppi
Active Contributor
0 Likes
1,299

Did you look on OSS notes, there is a KBA on BAdI for MRP:  2012620 - MRP: Problems with BAdIs

Hint: AFAIK this BAdI is related to the PR Enjoy transactions so may be not executed, nevertheless set "update debugging" on. Also ,check documentation at SPRO : Production, Material Requirements Planning, Business Add-Ins for Requirements Planning. (a ME BAdI on a MD transaction)


Regards,

Raymond

1 REPLY 1
Read only

RaymondGiuseppi
Active Contributor
0 Likes
1,300

Did you look on OSS notes, there is a KBA on BAdI for MRP:  2012620 - MRP: Problems with BAdIs

Hint: AFAIK this BAdI is related to the PR Enjoy transactions so may be not executed, nevertheless set "update debugging" on. Also ,check documentation at SPRO : Production, Material Requirements Planning, Business Add-Ins for Requirements Planning. (a ME BAdI on a MD transaction)


Regards,

Raymond