Adjust Modification during SP update

Former Member
0 Likes
823

Hi all,

We are doing the Solman 4.0 SP update to from sp11 to sp13, during the phase RUN_SPAU it's stopping with red light "Adjust modification".. I have make all the objects in SPAU to green and run the queue again .. still it's stopping at RUN_SPAU ?.

The object in the SPAU is BADI order_value , i have activated the object it's green now....

SPAU & SPDD objects are fine..... please suggest .... how to proceed further for SP update.

Thanks,

Subhash.G

5 REPLIES 5
Read only

Former Member
0 Likes
780

SP upgrade will prompt for SPDD first - Adjust Make it to green.

Then it will prompt for SPAU - Adjust and make it to green.

Hope you have done both SPDD and SPAU is fine right ?.

What is your problem now? Ask your basis team to continue the SP upgrade.

Read only

0 Likes
780

Thanks for quick reply, i am th Basis admin and i am doing SPAU with the help of ABAP developer.

There are no SPDD modifications, SPAU strangley we have modification to the Business-addons[BADI] in 000 client also..... i have made them green by activating it and it was green now.

When we start the SP upgrade still it stopping at Same phase.. Run_SPAU......

Please suggest..

Thanks,

Subhash.G

Read only

0 Likes
780

Hi,

Please check once in tcode SPAU all the check box are checked in the first 3 tabs. and Execute. You should not see any blue or red color. You should only see all green.

Edited by: senthil kumar on Oct 29, 2008 1:38 AM

Read only

0 Likes
780

Hi Kumar,

I have solved the problem, i have the started the queue process in dialog mode insted of Background .

Thanks,

Subhash.G

Read only

Former Member
0 Likes
780

Thnaks