I had merged my TR to another TR(The owner is different) and the my TR added as sub task for the other TR.Now my TR has been released and the main TR is not released yet.When I save my object one more subtask is getting generated under the main task.But I wantn a different TR under my EID.Can you please help how to do this?

Thanks in Advance.

1 ACCEPTED SOLUTION
Read only

Sandeep_Panghal
Product and Topic Expert
Product and Topic Expert
0 Likes
3,091

As your sub-task has been released and now if you want to make further changes it will ask for another taks if the same object is locked in this TR.

Here you have two options , release this TR and after that create a new TR and include the changes in this new TR or create a new sub-task under the old TR.

3 REPLIES 3
Read only

Sandeep_Panghal
Product and Topic Expert
Product and Topic Expert
0 Likes
3,092

As your sub-task has been released and now if you want to make further changes it will ask for another taks if the same object is locked in this TR.

Here you have two options , release this TR and after that create a new TR and include the changes in this new TR or create a new sub-task under the old TR.

Read only

Former Member
0 Likes
3,091

Hi,

You cannot save in a new TR unless the old main TR is released.

Regards,

Ankur Parab

Read only

praveen_hannu
Contributor
0 Likes
3,091

You have to release the old TR, then only you can save it into new TR.