on 04-07-2017 12:04 PM
In SAP MRS, I would like to know the possibility to create resource work schedule directly in MRS instead of integrate the resource work schedule from HCM.
Hello Dean Royston Pereira
This can be possible if you are using business partner (employee) as your resource.
If you are using HCM resource then then this is not possible to create work schedule, for HR resource availability is taken from planned working hours only.
Regards,
Kapil