on 06-16-2022 11:39 AM
GR time in the system (both in Apo and ECC) set as 19 days,but SNP Prereq is data is taking 25 as GR time.No changes has been made before and after creation of SNP Prereq value both in ECC and APO.How does this 25 value appears
Dear Sumanta, smells like a receiving calendar was maintained in the location master of the destination location tab "Calendars' which extends the 19 working days to 25 calendar days (+6 days eq. 3 weekends). If I remember correctly, then BAdI /sapapo/snpheu was extended lately to ignore the receiving calendar if the GR capacity consumption in the location product master ist initial.
Nico