on 05-06-2023 7:44 AM
Dear experts,
The start date and end date of the
production order are from April 11 to April
12, 2023. However, when the client tries to cancel
the order using CO13, an error message
appears: "Posting period 004 2023 is
locked (check posting date)." The client does not
want to open the period, so I would
appreciate it if you could suggest a
standard procedure for cancelling the
production order that I can suggest incase if opening the posting period is not an option . For example,
cancelling the posted document or
changing the date of posting.
Thank you in advance!
Hello pradeepkumar21,
If 04/2023 period is closed then it could be cancel or reverse the confirmations in the current period only
Regards,
Neeraj Jain
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
9 | |
8 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.