on 04-06-2016 1:38 PM
Dear Experts
I have a requirement to model transportation capacity in a transportation Lane. I have setup a Transportation resource with capacity maintained for this purpose as below:
This resource I am assigning to a Transportation Lane in the Means of Transport along with the consumption in Product-specific Means of Transport. In the Optimizer Results, it does show this transportation resource with the following resource capacity (1 TO per day for next 180 days).
However, it does not show the consumption. And it is not restricting the Stock Transfers by the transportation capacity.
I am unable to understand why it is not restricting the stock transfers / Fulfilled Demand by the capacity I have maintained.
Thanks,
Parth Soneji
Hi Parth,
Looks like 0 transport duration in mot is causing no resource consumption.
Thanks, Nikhil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Parth,
Is your optimizer profile discrete.
Thanks, Nikhil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
4 | |
3 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.