Need to schedule a maintenance order on particular date of the month like 6th and 21st which should have completion requirement.
I tried creating a factory calender with only 6th and 21st as work days. yet while i schedule the order i get the below error.
Key date will also not work since key date will only work with minimum 30 days and multiple of month. but my frequency is 15 days . any idea
Greetings,
you could try creating two maintenance plans. One for 6th day in the month and one for 21st day in month.
Best regards, Matjaž.