Hi Experts,

please help me with logic to find unsettled cost (4,439,763.86) on WBS as shown in below CJI3 report


Thanks in advance

unsettled-cost-for-wbs.png

Venkat

Accepted Solutions (0)

Answers (2)

Answers (2)

Ken_Melching
Product and Topic Expert
Product and Topic Expert

You need to examine CJI3N by bringing in the Cost Element. Settlement is all about cost elements. Then you'll have to go through the settlement configuration to make sure every cost element is accounted for.

TammyPowlas
Active Contributor

Hi - you could look at the logic of running transaction CJI3 or CJI3N, including the cost elements and the settlement elements. What remains is the unsettled costs. This is what our accountants do every month.