on 03-02-2021 9:31 AM
Hi Experts,
please help me with logic to find unsettled cost (4,439,763.86) on WBS as shown in below CJI3 report
Thanks in advance
unsettled-cost-for-wbs.pngVenkat
You need to examine CJI3N by bringing in the Cost Element. Settlement is all about cost elements. Then you'll have to go through the settlement configuration to make sure every cost element is accounted for.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi - you could look at the logic of running transaction CJI3 or CJI3N, including the cost elements and the settlement elements. What remains is the unsettled costs. This is what our accountants do every month.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
79 | |
10 | |
8 | |
4 | |
3 | |
3 | |
2 | |
2 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.