on 2024 Jun 17 6:20 PM
Hi ,
I am using gr processing time to fake a Md04 report . We increase number of days and it does update MD04 . Now I have a requirement in which Gr processing time should be in negative. Is it possible in standard ?
Request clarification before answering.
Hi @AAkash1
No, that's not possible - if it were, it would make scheduling go back in time. That's not possible unless in
You said you use GR processing time "to fake a Md04 report" - that doesn't sound right to fake anything in SAP.
If you describe your process and requirements in more detailed, maybe a more standard solution could be found.
Best regards
Dominik Tylczynski
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for your comments.
My process is
| User | Count |
|---|---|
| 22 | |
| 15 | |
| 14 | |
| 5 | |
| 4 | |
| 3 | |
| 2 | |
| 2 | |
| 2 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.