on 2015 Aug 17 7:41 AM
Hi All,
This is a query regarding the storage location not getting updated in refurbishment order in the component tab. As a practice task list should be attached in order but our user process is of slight vary. Pls find the process.
1. Create Maintenance Notification.
2. Attach task list in Notification & Save.
3. Create refurbishment order.
4. Linking of notification to refurbishment order through objects tab.
5. All the task list gets incorprated in operations tab.
We able to get the components linked in task list. But we are unable to get the storage locations of the same components.
Pls help on providing the solution. Also let me know in case of any further inputs on the same.
Best Regards
Ashish Rao
Hi Ashish,
Please maintain your required storage location at Prod. stor. location and Storage loc. for EP fileds in MRP2 tab using MM02 Tcode.
This will resolve your issue.
Regards
Vivek Patil.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Vivek,
Already its maintained. Nessesary actions is taken.
Note : If we are importing task list through Maintenance / Service order, then storage locations associated with materials is populated in components tab. But if we are following the above said process we are unable to get the storage locations.
Pls let me know in case of any further inputs required.
Best Regards
Ashish Rao
Hi Ashish,
Please check another option,For this you have to do following In Customizing :
Plant Maintenance and Customer Service>> Maintenance and Service Processing>> Maintenance
and Service Orders>> Functions and Settings for Order Types>>> Define Notification and Order Integration
Here you have to select: Assignment of Operation to All Notifications Active.
Regards
Vivek Patil.
Hi Ashish,
Check below screenshot
Functionality-When assigning a notification to an order, the automatic assignment of operations is possible for all notifications in the object list, that is for manually created notifications and for maintenance plan notifications.
You can display the operations and Components assigned to a notification.
Regards
Vivek Patil.
Hi Ashish,
Now last option is, check with "3 Assignment of Operation to All Object List Entries Active".
As we did checked all the available option.please check with above option.Before suggesting you, I simulated same scenario in my system and working fine.
If still you face same issue, Please take help from technical person to debug, why this field not getting populated.
Regards
Vivek Patil.