on 03-09-2011 2:43 PM
Hi All, I was wondering if there is a way to have the system confirm a partial quantity of a to position and make a split for the remaining. The issue that I`m having is that when I make a split for the position the system confirm both positions of the TO, the one created originally and the one created in the split. I guess, that this is the normal system behavior but I was wondering if that there is any way to solve this scenario, may be with a user exit or with 2 step process..
Thanks in advance
Kind Regards
Marcos
If you want debugging MWMTO002 --> EXIT_SAPLL03T_002.
You must set UPDATE TASK
Kind Regards
Nicolá
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
yes...possible through below exit
MWMTO002--->EXIT_SAPLL03T_002
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi! yes I do!!
thanks!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Do you have SU managment active?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.