on 12-18-2010 8:12 AM
Hi,
while creating service entry sheet, we can also maintain period start date and end date. Is there any possibility to update these dates to actual dates of corresponding service activity in the project.
Thanks & Regards
Siva
not possible in Std. SAP. you have to go for development. Look for some BADI's which triggers during save of service entry sheet.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.