Resource-secondary resource

raju_123
Participant
0 Kudos

Please advise how to assign secondary resource in master recipe operations? how to identify wheteher mentioned resource in operations / phases is primary or secondary resource?

Thank You.

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Just go to C202 enter your recipe number go in operation tab double clcik on operation or phase no go in details there you will get the secondary resource 4th tab. Where you can identify whether it is primary or secondary resource.

Regards,

R.Brahmankar

0 Kudos

Dear Brahmankar

could you please advice how to extract a list for secondary resource by value of recipe