TO not created immediately for PCN in WM after usage decision

Former Member
0 Kudos

Hi

when making usage decision for a batch produced in Q , the user is transfering a part of the quantity into unrestricted stock and the rest to blocked

Thus in MM 350 and 321 movements are made (one material document created)

In WM, the customizing is done to have 309 movement type interface with MM movement types (350 and 321) , with posting change notice creation and immediate TO creation

In LU04 i am finding 2 PCN still open

If i process manually the posting change notices , i succeed without any problem

I tested to have usage decision with 350 mvt type only => i get immediate TO creation for the PCN

I tested also usage decision with 321 mvt type only => i get immediate TO creation for the PCN

but the system is unable to process the PCNs when 2 movements types are used in MM

Can you help me understand why ? or advise me what could be wrong in the customizing?

Thank you

View Entire Topic
0 Kudos

One more: in your case assign both MvT: 350 and 321 with creation indicatoir. In variant for report RLAUTA11 mark also: Select Partially Processed TO (Automatic TO Generation)

former_member536836
Active Contributor
0 Kudos

Whatever Marcin has mentioned it is for automatic TO creation for PCN. I believe issue is how to create TO when you have some OK (unrestricted)material & some problematic(blocked)

Regards,

Prashant