Sorry, now I read it more carefully. If you don't run MRP - how you create Purchase Requisitions?I am affraid, without running MRP SAP could could not balance you stock wih demads so scenario with make to stock (that is you requirements) could not be...
Hello!i do not see any problem.Set up Material Master for all components:1. MRP view 4: individual/coll =2 (make to stock) 2. MRP view 3: Strategy group - make to stock3. Be sure that MRP group allows you to create PReq,. (MRP view 1)4. Create sours...
Hello!Go to MIGO transaction. In Top menu find ->Settings ->Default Values select "Propose All Items", press "Adopt". Go out from MIGO, go in and try again.Hope it helps.BR/Marcin
One more: in your case assign both MvT: 350 and 321 with creation indicatoir. In variant for report RLAUTA11 mark also: Select Partially Processed TO (Automatic TO Generation)
Hello!You do not need to create TO manually. Set up RLAUTA11 report as a job.To run RLAUTA11 you have to maitain: creation indicator: Logistic Execution->Warehouse Managment->Activities->Transfers->Set Up Autom. TO Creation for TRs / Posting Change N...