cancel
Showing results for 
Search instead for 
Did you mean: 

How to assign multiple work centres for one material ?

Ram_Thakur_9999
Explorer
0 Kudos
287

How do we assign multiple work centres for one material ?

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Ram

The questions you are asking are really basic production planning questions. Perhaps you should spend some time reading SAP Help and studying the basic features of PP.

Best regards,
Caetano Almeida

View Entire Topic
Caetano
Product and Topic Expert
Product and Topic Expert

Hello

You don't assign a work center directly to the material.

You will create a routing for your material, and this routing will have several operations, each one referring to a different work center.

Regards,
Caetano

Ram_Thakur_9999
Explorer
0 Kudos

Thank You Noted Sir