cancel
Showing results for 
Search instead for 
Did you mean: 

2I3, the commitment of the stock material purchase requisition is 0

Feng_Chen
Product and Topic Expert
Product and Topic Expert
313

Dear colleague,

This is PSCC China Group Chen, I am testing the scope item 2I3 as EPPM China customer need.

Testing system CCF 715.

I got one issue when I create stock material purchasing requisition: 10052551, material SG124

The account assignment is WBS: R21002

The comment is 0.

But when I create the non-stock material purchasing requisition: 10052531

The system could get the commitment.

So when I run the report, here is the result.

I checked the scope item, this should work for both stock and non-stock.

Could you help to support which configuration should be changed then the commitment could work for stock purchasing?

Many thanks

Chen

View Entire Topic
Raman_Rana
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi,

Good day.

Can you recheck your GL assignment to Tag ACT_COST and semantic tag assignment to FSV?.

regards, Raman Rana

Feng_Chen
Product and Topic Expert
Product and Topic Expert
0 Kudos

Dear colleague,

As I am not a finance expert. Could I know which SSCUI or APP check the GL assignment to Tag ACT_COST?

Many thanks,

Chen